Phase 1
Core
Kickoff (~1 week)
The Project Kickoff Call serves as the project kickoff between the client team and the PrestoSports team. During this time we will make introductions for all team members on the call and will have a high-level overview of the entire project plan.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Project Kickoff Call |
✔ |
✔ |
Upload images and other content for the Site |
✔ |
|
Submit Design Form |
✔ |
|
DNS setup and configuration |
✔ |
✔ |
Pro
Kickoff (~1 week)
The Project Kickoff Call serves as the project kickoff between the client team and the PrestoSports team. During this time we will make introductions for all team members on the call and will have a high-level overview of the entire project plan.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Project Kickoff Call |
✔ |
✔ |
Upload images and other content for the Site |
✔ |
|
Submit Design Form |
✔ |
|
DNS setup and configuration |
✔ |
✔ |
Premium
Kickoff (~1 week)
The Project Kickoff Call serves as the project kickoff between the client team and the PrestoSports team. During this time we will make introductions for all team members on the call and will have a high-level overview of the entire project plan.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Project Kickoff Call |
✔ |
✔ |
Upload images and other content for the Site |
✔ |
|
Submit Design Form |
✔ |
|
DNS setup and configuration |
✔ |
✔ |
Phase 2
Core
Site Set Up (~ 3 to 4 weeks)
Set up of site based on the submitted design form and media collateral, the configuration functional application framework (i.e. page layouts, module placement, and navigation setup).
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Site build based on submitted design form |
✔ |
|
Site breakdown and implementation of features |
✔ |
|
Review of site design; up to three (3) rounds of revisions allowed; approve final design |
✔ |
Pro
Site Design (~ 3 to 4 weeks)
A PDF Design file is created for the site based on the submitted design form and media collateral, the configuration functional application framework (i.e. page layouts, module placement, and navigation setup.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
A PDF Design file based on submitted design form |
✔ |
|
Review of site design; up to three (3) rounds of revisions allowed; approve final design |
|
✔ |
Design Revisions per client requests for updated PDF Design File |
✔ |
|
Preparation of design assets for front end development |
✔ |
|
Premium
Site Design (~ 4 to 6 weeks)
A PDF Design file is created for the site based on the submitted design form and media collateral, the configuration functional application framework (i.e. page layouts, module placement, and navigation setup.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
A PDF Design file based on submitted design form |
✔ |
|
Review of site design; up to three (3) rounds of revisions allowed; approve final design |
|
✔ |
Design Revisions per client requests for updated PDF Design File |
✔ |
|
Preparation of design assets for front end development |
✔ |
|
Phase 3
Core
Content Loading & Review (~ 3 to 4 weeks)
Using the Content Management System, modules and plugins to enter content into website completing Site Build.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Introduction to the PrestoSports administrative system |
✔ |
|
Data Migration* |
✔ |
|
Content Loading** |
✔ |
Pro
Site Set Up (~ 3 to 4 weeks)
Set up of site based on the submitted design form and media collateral, the configuration functional application framework (i.e. page layouts, module placement, and navigation setup).
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Site build based on approved design file |
✔ |
|
Site breakdown and implementation of features |
✔ |
Premium
Site Set Up (~ 8 to 10 weeks)
Set up of site based on the submitted design form and media collateral, the configuration functional application framework (i.e. page layouts, module placement, and navigation setup).
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Site build based on approved design file |
✔ |
|
Site breakdown and implementation of features |
✔ |
Phase 4
Pro
Content Loading & Review (~ 3 to 4 weeks)
Using the Content Management System, modules and plugins to enter content into website completing Site Build.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Introduction to the PrestoSports administrative system |
✔ |
|
Data Migration* |
✔ |
|
Content Loading** |
✔ |
Premium
Content Loading & Review (~ 3 to 4 weeks)
Using the Content Management System, modules and plugins to enter content into website completing Site Build.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Introduction to the PrestoSports administrative system |
✔ |
|
Data Migration* |
✔ |
|
Content Loading** |
✔ |
Phase 5
Core
Get to work promoting your site!
Pro
Review & Quality Control (~ 3 weeks)
Team review of website content, usability, and functionality. Modifications made when necessary.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Continued data migration and training |
|
✔ |
Register URL to search engines |
✔ |
|
Quality control on Site |
✔ |
✔ |
ADA Compliance Review |
✔ |
|
Premium
Review & Quality Control (~ 3 weeks)
Team review of website content, usability, and functionality. Modifications made when necessary.
Action |
Responsible Party |
|
PrestoSports |
Client |
|
Continued data migration and training |
|
✔ |
Register URL to search engines |
✔ |
|
Quality control on Site |
✔ |
✔ |
ADA Compliance Review |
✔ |
|